RIALTO PRIMARY CARE CENTRE, DUBLIN 8

This project involved the demolition of 379 and 383 South Circular Road, Rialto, Dublin 8 and the construction of a new 3 storey over a single level basement Primary Care Centre.

A single external ramp alongside the west facing elevation provides vehicular access into a concealed basement car park which was constructed utilising a secant piled wall for excavation. The basement is a Grade 1 reinforced concrete basement with a preprufe membrane.  An attenuation tank is installed at basement level together with other plant requirements for the building.

The structure is reinforced concrete columns with flat slab and infill blockwork.

DATE 2017-2019

CLIENT Rialto PCC Ltd.

SIZE 3358 sq.m

Civil & Structural Engineering Services

Ancillary Certifier

Traffic Engineering Services